Friday, January 4, 2008

Activity Duration Estimation

What is Activity Duration Estimation?

Activity Duration Estimation is the act of estimating the number of work units needed to complete individual project activities and this shapes the preliminary project schedule.

What are the key terms in Activity Duration Estimation?
  • Elapsed Time
    This is the actual calender days/months/years required for an activity from start to finish.

  • Effort
    This is the number of person-hours or persons-days required to complete the activity.
    This estimates the effort to be provided based on the cost estimation and resources estimation.

No comments:

Post a Comment