1. In a weak matrix, the majority of the project authority is held by:
A. Functional Manager
B. Team Member
C. Project Manager
D. Technical Manager
2. Project team member are most likely to work full-time on a project in which of the following organizational structures?
A. Functional
B. Weak Matrix
C. Strong Matrix
D. Projectized
3. Tim is the project manager of the XXX project. His organization is a classic functional environment. His level of authority as a project manager can be best described as:
A. Low
B. Moderate
C. Balanced
D. High
4. Complex projects involving cross-disciplinary efforts are most effective managed by:
A. Multiple lead project manager
B. A function organization
C. A strong matrix organization
D. A strong traditional manager
(To see the answers, highlight this whole topic by right click on the mouse and drag down. If you are not able to do this, please leave me a comment.)
Answers:
1. A
2. D
3. A
4. C
2 comments:
i can not see the answers
Post a Comment