Organizational Structure Pop Quiz for PMP Exam

1. In a weak matrix, the majority of the project authority is held by:
A. Functional Manager
B. Team Member
C. Project Manager
D. Technical Manager


2. Project team member are most likely to work full-time on a project in which of the following organizational structures?
A. Functional
B. Weak Matrix
C. Strong Matrix
D. Projectized


3. Tim is the project manager of the XXX project. His organization is a classic functional environment. His level of authority as a project manager can be best described as:
A. Low
B. Moderate
C. Balanced
D. High


4. Complex projects involving cross-disciplinary efforts are most effective managed by:
A. Multiple lead project manager
B. A function organization
C. A strong matrix organization
D. A strong traditional manager

(To see the answers, highlight this whole topic by right click on the mouse and drag down. If you are not able to do this, please leave me a comment.)

Answers:
1. A
2. D
3. A
4. C

2 comments:

ProXalt said...
This comment has been removed by the author.
Unknown said...

i can not see the answers

Suggested Study Materials

  • PMP-Preparation Recommended Books
  • PMP Exam Prep, Fifth Edition: Rita's Course in a Book for Passing the PMP Exam
  • A Guide to the Project Management Body of Knowledge, Third Edition (PMBOK Guides)
  • The PMP Exam: How to Pass On Your First Try (Test Prep series)