- Mandatory / Hard Logic
- Inherent in the nature of work done. - External
- Based on the needs of a party outside of the project. - Discretionary
- Dependencies defined by Project Management Team at their discretion.
- There is no choice between Mandatory and External Dependencies.
- This is the preferred method of arranging activities based on conditions, guidelines or best practices.
This site contains information for your preparation of PMI's PMP (Project Management Professional) certification exam. I have also Included topics on how to pass the exam and some mock exams.
Saturday, December 29, 2007
Activity Dependencies
Types of Activity Dependencies include:
Subscribe to:
Post Comments (Atom)
Suggested Study Materials
- PMP-Preparation Recommended Books
- PMP Exam Prep, Fifth Edition: Rita's Course in a Book for Passing the PMP Exam
- A Guide to the Project Management Body of Knowledge, Third Edition (PMBOK Guides)
- The PMP Exam: How to Pass On Your First Try (Test Prep series)
No comments:
Post a Comment