Q1
Stakeholders have ability to influence the final outcome of the project:
A. Later in the project life cycle
B. Earlier in the project life cycle
C. Anytime during the project life cycle
D. earlier in the project life cycle but increase over the life of the cycle

Q2
All of the following are part of the team's stakeholder management effort except?
A. Giving stateholder extra
B. Indentify stakeholder
C. Determining stakeholders needs
D. Managing stakeholders expectation

(To see the answers, highlight this whole topic by right click on the mouse and drag down. If you are not able to do this, please leave me a comment.)





ANS:
Q1 - C (Stakeholder has influence throughout the project life cycle)
Q2 - A (In PMP, you should give the stakeholder no more no less)

1 comment:

Olivia Jennifer said...

I would say that a PMP is highly respected within both IT & non-IT communities where strong project management skills are required. If you plan on a long term career as a project manager, then yes, even with your level of experience, I would suggest getting your PMP. You can prepare yourself for the exam in one of the leading training providers like http://www.pmstudy.com . You can do minimal prep-work to get 40 PMI® Contact Hours and apply to PMI for PMP Exam before the class begins.

Recommended Books on PMP

Suggested Study Materials

  • PMP-Preparation Recommended Books
  • PMP Exam Prep, Fifth Edition: Rita's Course in a Book for Passing the PMP Exam
  • A Guide to the Project Management Body of Knowledge, Third Edition (PMBOK Guides)
  • The PMP Exam: How to Pass On Your First Try (Test Prep series)