For CPM, I have listed the following key terms:

  • Free Float
    This is the total time a single activity can be delayed without delayhing the early start of any successor activities.

  • Total Slack
    This is the total time an activity can be delayed without delaying project completion.

  • Project Slack
    This is the total time the project can be delayed without passing the customer expected completion date.